Rate analysis
Dismantling wooden ballies in posts and struts including stacking within 50metres lead.
DSR rate₹20.95as per item analysis
- Item code
- 15.33
- Sub-head
- SH 15 · DISMANTLING
- Unit
- See analysis
- Source row
- 937
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Detail of cost for 50 metre | |||||
| LABOUR | |||||
| 0114 | Beldar | day | 0.5 | ₹736.00 | ₹368.00 |
| 0115 | Coolie | day | 0.5 | ₹736.00 | ₹368.00 |
| 9999 | Sundries | L.S. | 0.52 | ₹2.27 | ₹1.18 |
Rate build-up
| TOTAL | ₹737.18 |
| Add 1 % Water charges on "W" | ₹7.37 |
| TOTAL | ₹744.55 |
| Add GST on "X" (multiplying factor 0.2127) | ₹158.37 |
| TOTAL | ₹902.92 |
| Add 15% CPOH on "Y" | ₹135.44 |
| TOTAL | ₹1,038.36 |
| Add Cess @ 1% on "Z" | ₹10.38 |
| Cost of 50.00 metre | ₹1,048.74 |
| Cost of 1.00 metre | ₹20.97 |
| Say | ₹20.95 |