DSR 2023 · SH 15 · DISMANTLING

CPWD DSR item 15.34.2 rate analysis

Dismantling and stacking within 50 metres lead, fencing posts or struts including all earth work and dismantling of concrete etc. in base of: R.C.C.

Published rate₹243.30DSR 2023
Rate analysis

Dismantling and stacking within 50 metres lead, fencing posts or struts including all earth work and dismantling of concrete etc. in base of:

DSR rate₹243.30as per item analysis

R.C.C.

Item code
15.34.2
Sub-head
SH 15 · DISMANTLING
Unit
See analysis
Source row
956

Cost components

CodeDescriptionUnitQuantityRateAmount
Detail of cost for each
LABOUR
0114 Beldar day 0.097 ₹736.00 ₹71.39
0115 Coolie day 0.06 ₹736.00 ₹44.16
9999 Sundries L.S. 0.26 ₹2.27 ₹0.59
9999 Excavation, transporting and stacking the posts to the required place within 50 metres lead, refilling the pit and dressing the same L.S. 13.39 ₹2.27 ₹30.40
9999 Extra for lifting of R.C.C. posts being heavier than L iron and cleaning the posts of stacking concrete L.S. 8.06 ₹2.27 ₹18.30
9999 Sundries L.S. 2.73 ₹2.27 ₹6.20

Rate build-up

TOTAL ₹171.04
Add 1 % Water charges on "W" ₹1.71
TOTAL ₹172.75
Add GST on "X" (multiplying factor 0.2127) ₹36.74
TOTAL ₹209.49
Add 15% CPOH on "Y" ₹31.42
TOTAL ₹240.91
Add Cess @ 1% on "Z" ₹2.41
Cost of each ₹243.32
Say ₹243.30