Rate analysis
Dismantling and stacking within 50 metres lead, fencing posts or struts including all earth work and dismantling of concrete etc. in base of:
DSR rate₹243.30as per item analysis
R.C.C.
- Item code
- 15.34.2
- Sub-head
- SH 15 · DISMANTLING
- Unit
- See analysis
- Source row
- 956
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Detail of cost for each | |||||
| LABOUR | |||||
| 0114 | Beldar | day | 0.097 | ₹736.00 | ₹71.39 |
| 0115 | Coolie | day | 0.06 | ₹736.00 | ₹44.16 |
| 9999 | Sundries | L.S. | 0.26 | ₹2.27 | ₹0.59 |
| 9999 | Excavation, transporting and stacking the posts to the required place within 50 metres lead, refilling the pit and dressing the same | L.S. | 13.39 | ₹2.27 | ₹30.40 |
| 9999 | Extra for lifting of R.C.C. posts being heavier than L iron and cleaning the posts of stacking concrete | L.S. | 8.06 | ₹2.27 | ₹18.30 |
| 9999 | Sundries | L.S. | 2.73 | ₹2.27 | ₹6.20 |
Rate build-up
| TOTAL | ₹171.04 |
| Add 1 % Water charges on "W" | ₹1.71 |
| TOTAL | ₹172.75 |
| Add GST on "X" (multiplying factor 0.2127) | ₹36.74 |
| TOTAL | ₹209.49 |
| Add 15% CPOH on "Y" | ₹31.42 |
| TOTAL | ₹240.91 |
| Add Cess @ 1% on "Z" | ₹2.41 |
| Cost of each | ₹243.32 |
| Say | ₹243.30 |