Rate analysis
Deduct for not rolling with power roller of minimum 8 tonnes for banking excavated earth in layers not exceeding 20 cm in depth.
DSR rate₹5.25per cum
- Item code
- 2.4
- Sub-head
- SH 2 · EARTH WORK
- Unit
- cum
- Source row
- 74
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 10 cum. | |||||
| LABOUR | |||||
| 0113 | Chowkidar | day | 0.008 | ₹736.00 | ₹5.89 |
| 0003 | Hire charges of Diesel Road Roller - 8 to 10 tonne | day | 0.008 | ₹3,350.00 | ₹26.80 |
| 9999 | Sundries | L.S. | 1.82 | ₹2.27 | ₹4.13 |
Rate build-up
| TOTAL | ₹36.82 |
| Add 1 % Water charges on "W" | ₹0.37 |
| TOTAL | ₹37.19 |
| Add GST on "X" (multiplying factor 0.2127) | ₹7.91 |
| TOTAL | ₹45.10 |
| Add 15% CPOH on "Y" | ₹6.77 |
| TOTAL | ₹51.87 |
| Add Cess @ 1% on "Z" | ₹0.52 |
| Cost of 10 cum. | ₹52.39 |
| Cost of 1 cum. | ₹5.24 |
| Say | ₹5.25 |