DSR 2023 · SH 2 · EARTH WORK

CPWD DSR item 2.3.1 rate analysis

Banking excavated earth by mechanical / manual means in layers not exceeding 20 cm in depth, breaking clods, watering, rolling each layer with ½ tonne roller, or wooden or steel rammers, and rolling every 3rd and top-most layer with power roller of minimum 8 tonnes and dressing up, in embankments for roads, flood banks, marginal banks, and guide banks etc., lead upto 50 m and for all lift : All kinds of soil

Published rate₹197.90per cum
Rate analysis

Banking excavated earth by mechanical / manual means in layers not exceeding 20 cm in depth, breaking clods, watering, rolling each layer with ½ tonne roller, or wooden or steel rammers, and rolling every 3rd and top-most layer with power roller of minimum 8 tonnes and dressing up, in embankments for roads, flood banks, marginal banks, and guide banks etc., lead upto 50 m and for all lift :

DSR rate₹197.90per cum

All kinds of soil

Item code
2.3.1
Sub-head
SH 2 · EARTH WORK
Unit
cum
Source row
49

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10 cum.
MACHINERY
0049 Dozer 80 HP for spreading hour 0.374 ₹1,700.00 ₹635.80
0050 Motor grader for grading hour 0.167 ₹2,700.00 ₹450.90
0054 Vibrator roller 8-10 tonne hour 0.167 ₹700.00 ₹116.90
0057 Water tanker 6 KL capacity hour 0.4 ₹250.00 ₹100.00
LABOUR
0128 Mate day 0.004 ₹816.00 ₹3.26
0115 Coolie day 0.1 ₹736.00 ₹73.60
9999 Sundries (i.e. watch and ward, minor T&P etc.) L.S. 4.61 ₹2.27 ₹10.46

Rate build-up

TOTAL ₹1,390.92
Add 1 % Water charges on "W" ₹13.91
TOTAL ₹1,404.83
Add GST on "X" (multiplying factor 0.2127) ₹298.81
TOTAL ₹1,703.64
Add 15% CPOH on "Y" ₹255.55
TOTAL ₹1,959.19
Add Cess @ 1% on "Z" ₹19.59
Cost of 10 cum. ₹1,978.78
Cost of 1 cum. ₹197.88
Say ₹197.90