DSR 2023 · SH 2 · EARTH WORK

CPWD DSR item 2.5 rate analysis

Deduct for not watering the excavated earth for banking

Published rate₹14.25per cum
Rate analysis

Deduct for not watering the excavated earth for banking

DSR rate₹14.25per cum
Item code
2.5
Sub-head
SH 2 · EARTH WORK
Unit
cum
Source row
93

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10 cum.
MACHINERY
0057 Water tanker 6 KL capacity hour 0.4 ₹250.00 ₹100.00

Rate build-up

TOTAL ₹100.00
Add 1 % Water charges on "W" ₹1.00
TOTAL ₹101.00
Add GST on "X" (multiplying factor 0.2127) ₹21.48
TOTAL ₹122.48
Add 15% CPOH on "Y" ₹18.37
TOTAL ₹140.85
Add Cess @ 1% on "Z" ₹1.41
Cost of 10 cum. ₹142.26
Cost of 1 cum. ₹14.23
Say ₹14.25