Rate analysis
Deduct for not watering the excavated earth for banking
DSR rate₹14.25per cum
- Item code
- 2.5
- Sub-head
- SH 2 · EARTH WORK
- Unit
- cum
- Source row
- 93
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 10 cum. | |||||
| MACHINERY | |||||
| 0057 | Water tanker 6 KL capacity | hour | 0.4 | ₹250.00 | ₹100.00 |
Rate build-up
| TOTAL | ₹100.00 |
| Add 1 % Water charges on "W" | ₹1.00 |
| TOTAL | ₹101.00 |
| Add GST on "X" (multiplying factor 0.2127) | ₹21.48 |
| TOTAL | ₹122.48 |
| Add 15% CPOH on "Y" | ₹18.37 |
| TOTAL | ₹140.85 |
| Add Cess @ 1% on "Z" | ₹1.41 |
| Cost of 10 cum. | ₹142.26 |
| Cost of 1 cum. | ₹14.23 |
| Say | ₹14.25 |