DSR 2023 · SH 2 · EARTH WORK

CPWD DSR item 2.37 rate analysis

Supply and stacking of Fly ash conforming to IRC- 58 at site, including carriage, loading , unloading & stacking up to any lead (measured stacks will be reduced by 20% for payment).

Published rate₹281.05per cum
Rate analysis

Supply and stacking of Fly ash conforming to IRC- 58 at site, including carriage, loading , unloading & stacking up to any lead (measured stacks will be reduced by 20% for payment).

DSR rate₹281.05per cum
Item code
2.37
Sub-head
SH 2 · EARTH WORK
Unit
cum
Source row
2143

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 1 cum.
Ref :- Based on DAR Item No : 1.1.1
Labour and carriage
1980 Flyash cum 1 ₹12.00 ₹12.00
(Available free of cost at thermal power plant at Baderpur power plant. Lead = 35 km)
2262 Carriage of Flyash cum 1 ₹185.55 ₹185.55
(1st Lead 0 to 5km)

Rate build-up

TOTAL ₹197.55
Add 1 % Water charges on "W" ₹1.98
TOTAL ₹199.53
Add GST on "X" (multiplying factor 0.2127) ₹42.44
TOTAL ₹241.97
Add 15% CPOH on "Y" ₹36.30
TOTAL ₹278.27
Add Cess @ 1% on "Z" ₹2.78
Cost of 1 cum. ₹281.05
Say ₹281.05