DSR 2023 · SH 2 · EARTH WORK

CPWD DSR item 2.38 rate analysis

Filling with available fly ash and earth (excluding rock) in trenches or embankment in layers (each layer should not exceed 15 cm), with intermediate layer of compacted earth (Soil density of 98%) after every four layers of compacted depth of fly ash, sides & top layer of filling shall be done with earth having total minimum compacted thickness 30 cm or as decided by Engineer -in-charge, including compacting each layer by rolling/ ramming and watering, all complete as per drawing and direction of Engineer -in - charge.

Published rate₹308.20per cum
Rate analysis

Filling with available fly ash and earth (excluding rock) in trenches or embankment in layers (each layer should not exceed 15 cm), with intermediate layer of compacted earth (Soil density of 98%) after every four layers of compacted depth of fly ash, sides & top layer of filling shall be done with earth having total minimum compacted thickness 30 cm or as decided by Engineer -in-charge, including compacting each layer by rolling/ ramming and watering, all complete as per drawing and direction of Engineer -in - charge.

DSR rate₹308.20per cum
Item code
2.38
Sub-head
SH 2 · EARTH WORK
Unit
cum
Source row
2163

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10 cum.
Ref :- Based on DAR Item No : 2.25
LABOUR
0128 Mate day 0.2 ₹816.00 ₹163.20
0115 Coolie day 2.5 ₹736.00 ₹1,840.00
0101 Bhisti day 0.2 ₹816.00 ₹163.20

Rate build-up

TOTAL ₹2,166.40
Add 1 % Water charges on "W" ₹21.66
TOTAL ₹2,188.06
Add GST on "X" (multiplying factor 0.2127) ₹465.40
TOTAL ₹2,653.46
Add 15% CPOH on "Y" ₹398.02
TOTAL ₹3,051.48
Add Cess @ 1% on "Z" ₹30.51
Cost of 10 cum. ₹3,081.99
Cost of 1 cum. ₹308.20
Say ₹308.20