Rate analysis
Extra for levelling & neatly dressing of disposed soil completely as directed by Engineer-in-charge.
DSR rate₹93.05per cum
- Item code
- 2.36
- Sub-head
- SH 2 · EARTH WORK
- Unit
- cum
- Source row
- 2125
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 10 cum. | |||||
| LABOUR | |||||
| 0128 | Mate | day | 0.08 | ₹816.00 | ₹65.28 |
| 0115 | Beldar/ Coolie | day | 0.8 | ₹736.00 | ₹588.80 |
Rate build-up
| TOTAL | ₹654.08 |
| Add 1 % Water charges on "W" | ₹6.54 |
| TOTAL | ₹660.62 |
| Add GST on "X" (multiplying factor 0.2127) | ₹140.51 |
| TOTAL | ₹801.13 |
| Add 15% CPOH on "Y" | ₹120.17 |
| TOTAL | ₹921.30 |
| Add Cess @ 1% on "Z" | ₹9.21 |
| Cost of 10 cum. | ₹930.51 |
| Cost of 1 cum. | ₹93.05 |
| Say | ₹93.05 |