Rate analysis
Diluting and injecting chemical emulsion for POST-CONSTRUCTIONAL anti-termite treatment (excluding the cost of chemical emulsion) : Along the external wall below concrete or masonry apron using chemical emulsion @ 2.25 litres per linear metre including drilling and plugging holes etc.:
DSR rate₹53.45as per item analysis
With Chlorpyriphos/ Lindane E.C. 20% with 1% concentration
- Item code
- 2.35.2.1
- Sub-head
- SH 2 · EARTH WORK
- Unit
- See analysis
- Source row
- 1996
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 10 metres | |||||
| MATERIAL | |||||
| Chlorpyriphos 1% concentration = 10x 2.25 = 22.5 litres | |||||
| Chlorpyriphos 20% required = 22.50/20 = 1.125 litres | |||||
| Chlorpyriphos 20% E.C. / Lindane 20% E.C. 1.125 litres (to be supplied free of cost) | |||||
| LABOUR | |||||
| 0114 | Beldar | day | 0.4 | ₹736.00 | ₹294.40 |
| (for drilling holes and injecting chemical) | |||||
| 9999 | Sundries and rent of a sprayer and mortar and making good the holes | L.S. | 35.88 | ₹2.27 | ₹81.45 |
Rate build-up
| TOTAL | ₹375.85 |
| Add 1 % Water charges on "W" | ₹3.76 |
| TOTAL | ₹379.61 |
| Add GST on "X" (multiplying factor 0.2127) | ₹80.74 |
| TOTAL | ₹460.35 |
| Add 15% CPOH on "Y" | ₹69.05 |
| TOTAL | ₹529.40 |
| Add Cess @ 1% on "Z" | ₹5.29 |
| Cost for 10 metres | ₹534.69 |
| Cost for 1 metre | ₹53.47 |
| Say | ₹53.45 |