DSR 2023 · SH 2 · EARTH WORK

CPWD DSR item 2.35.2.1 rate analysis

Diluting and injecting chemical emulsion for POST-CONSTRUCTIONAL anti-termite treatment (excluding the cost of chemical emulsion) : Along the external wall below concrete or masonry apron using chemical emulsion @ 2.25 litres per linear metre including drilling and plugging holes etc.: With Chlorpyriphos/ Lindane E.C. 20% with 1% concentration

Published rate₹53.45DSR 2023
Rate analysis

Diluting and injecting chemical emulsion for POST-CONSTRUCTIONAL anti-termite treatment (excluding the cost of chemical emulsion) : Along the external wall below concrete or masonry apron using chemical emulsion @ 2.25 litres per linear metre including drilling and plugging holes etc.:

DSR rate₹53.45as per item analysis

With Chlorpyriphos/ Lindane E.C. 20% with 1% concentration

Item code
2.35.2.1
Sub-head
SH 2 · EARTH WORK
Unit
See analysis
Source row
1996

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10 metres
MATERIAL
Chlorpyriphos 1% concentration = 10x 2.25 = 22.5 litres
Chlorpyriphos 20% required = 22.50/20 = 1.125 litres
Chlorpyriphos 20% E.C. / Lindane 20% E.C. 1.125 litres (to be supplied free of cost)
LABOUR
0114 Beldar day 0.4 ₹736.00 ₹294.40
(for drilling holes and injecting chemical)
9999 Sundries and rent of a sprayer and mortar and making good the holes L.S. 35.88 ₹2.27 ₹81.45

Rate build-up

TOTAL ₹375.85
Add 1 % Water charges on "W" ₹3.76
TOTAL ₹379.61
Add GST on "X" (multiplying factor 0.2127) ₹80.74
TOTAL ₹460.35
Add 15% CPOH on "Y" ₹69.05
TOTAL ₹529.40
Add Cess @ 1% on "Z" ₹5.29
Cost for 10 metres ₹534.69
Cost for 1 metre ₹53.47
Say ₹53.45