DSR 2023 · SH 2 · EARTH WORK

CPWD DSR item 2.35.1.1 rate analysis

Diluting and injecting chemical emulsion for POST-CONSTRUCTIONAL anti-termite treatment (excluding the cost of chemical emulsion) : Along external wall where the apron is not provided using chemical emulsion @ 7.5 litres / sqm of the vertical surface of the substructure to a depth of 300mm including excavation channel along the wall & rodding etc. complete: With Chlorpyriphos/ Lindane E.C. 20% with 1% concentration

Published rate₹38.90DSR 2023
Rate analysis

Diluting and injecting chemical emulsion for POST-CONSTRUCTIONAL anti-termite treatment (excluding the cost of chemical emulsion) : Along external wall where the apron is not provided using chemical emulsion @ 7.5 litres / sqm of the vertical surface of the substructure to a depth of 300mm including excavation channel along the wall & rodding etc. complete:

DSR rate₹38.90as per item analysis

With Chlorpyriphos/ Lindane E.C. 20% with 1% concentration

Item code
2.35.1.1
Sub-head
SH 2 · EARTH WORK
Unit
See analysis
Source row
1996

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10 metres
MATERIAL
Chlorpyriphos 1% concentration = 10.0x 0.30x7.5 = 22.5 litres
Chlorpyriphos 20% required = 22.5/20 = 1.125 litres
Chlorpyriphos 20% E.C. / Lindane 20% E.C. 1.125 litres (to be supplied free of cost)
LABOUR
0114 Beldar day 0.33 ₹736.00 ₹242.88
(for excavating channel) rodding in chemical spraying the emulssion and refilling the same
9999 Sundries, rent of sprayer etc. L.S. 13.52 ₹2.27 ₹30.69

Rate build-up

TOTAL ₹273.57
Add 1 % Water charges on "W" ₹2.74
TOTAL ₹276.31
Add GST on "X" (multiplying factor 0.2127) ₹58.77
TOTAL ₹335.08
Add 15% CPOH on "Y" ₹50.26
TOTAL ₹385.34
Add Cess @ 1% on "Z" ₹3.85
Cost for 10 metres ₹389.19
Cost for 1 metre ₹38.92
Say ₹38.90

Use this rate in the interactive workbook