DSR 2023 · SH 2 · EARTH WORK

CPWD DSR item 2.30.4 rate analysis

Hard rock (blasting prohibited)

Published rate₹461.30per hole
Rate analysis

Hard rock (blasting prohibited)

DSR rate₹461.30per hole
Item code
2.30.4
Sub-head
SH 2 · EARTH WORK
Unit
hole
Source row
1838

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10 holes-
Earth work 10 x 0.3 (avg) = 3.0 cum
2.9.3 Rate as per Item Number 2.9.3 of SH: Earth Work cum 3 ₹1,523.05 ₹4,569.15
Extra labour for filling and ramming
9999 Sundries L.S. 13.52 ₹2.27 ₹30.69

Rate build-up

TOTAL ₹4,599.84
Add 1 % Water charges on "W-A" ₹0.31
TOTAL ₹4,600.15
Add GST on "X-A" (multiplying factor 0.2127) ₹6.59
TOTAL ₹4,606.74
Add 15% CPOH on "Y-A" ₹5.64
TOTAL ₹4,612.38
Add Cess @ 1% on "Z-A" ₹0.43
Cost of 10 holes ₹4,612.81
Cost of 1 hole ₹461.28
Say ₹461.30