DSR 2023 · SH 2 · EARTH WORK

CPWD DSR item 2.31 rate analysis

Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth up to 30 cm measured at a height of 1 m above ground level and removal of rubbish up to a distance of 50 m outside the periphery of the area cleared.

Published rate₹17.60per sqm
Rate analysis

Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth up to 30 cm measured at a height of 1 m above ground level and removal of rubbish up to a distance of 50 m outside the periphery of the area cleared.

DSR rate₹17.60per sqm
Item code
2.31
Sub-head
SH 2 · EARTH WORK
Unit
sqm
Source row
1857

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 100 sqm.
LABOUR
0114 Beldar day 1.08 ₹736.00 ₹794.88
0115 Coolie day 0.6 ₹736.00 ₹441.60

Rate build-up

TOTAL ₹1,236.48
Add 1 % Water charges on "W" ₹12.36
TOTAL ₹1,248.84
Add GST on "X" (multiplying factor 0.2127) ₹265.63
TOTAL ₹1,514.47
Add 15% CPOH on "Y" ₹227.17
TOTAL ₹1,741.64
Add Cess @ 1% on "Z" ₹17.42
Cost of 100 sqm. ₹1,759.06
Cost of 1 sqm. ₹17.59
Say ₹17.60