Rate analysis
Clearing jungle including uprooting of rank vegetation, grass, brush wood, trees and saplings of girth up to 30 cm measured at a height of 1 m above ground level and removal of rubbish up to a distance of 50 m outside the periphery of the area cleared.
DSR rate₹17.60per sqm
- Item code
- 2.31
- Sub-head
- SH 2 · EARTH WORK
- Unit
- sqm
- Source row
- 1857
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 100 sqm. | |||||
| LABOUR | |||||
| 0114 | Beldar | day | 1.08 | ₹736.00 | ₹794.88 |
| 0115 | Coolie | day | 0.6 | ₹736.00 | ₹441.60 |
Rate build-up
| TOTAL | ₹1,236.48 |
| Add 1 % Water charges on "W" | ₹12.36 |
| TOTAL | ₹1,248.84 |
| Add GST on "X" (multiplying factor 0.2127) | ₹265.63 |
| TOTAL | ₹1,514.47 |
| Add 15% CPOH on "Y" | ₹227.17 |
| TOTAL | ₹1,741.64 |
| Add Cess @ 1% on "Z" | ₹17.42 |
| Cost of 100 sqm. | ₹1,759.06 |
| Cost of 1 sqm. | ₹17.59 |
| Say | ₹17.60 |