Rate analysis
Hard rock (requiring blasting)
DSR rate₹319.30per hole
- Item code
- 2.30.3
- Sub-head
- SH 2 · EARTH WORK
- Unit
- hole
- Source row
- 1819
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 10 holes- | |||||
| Earth work 10 x 0.3 (avg) = 3.0 cum | |||||
| 2.9.2 | Rate as per Item Number 2.9.2 of SH: Earth Work | cum | 3 | ₹1,049.80 | ₹3,149.40 |
| Extra labour for filling and ramming | |||||
| 9999 | Sundries | L.S. | 13.52 | ₹2.27 | ₹30.69 |
Rate build-up
| TOTAL | ₹3,180.09 |
| Add 1 % Water charges on "W-A" | ₹0.31 |
| TOTAL | ₹3,180.40 |
| Add GST on "X-A" (multiplying factor 0.2127) | ₹6.59 |
| TOTAL | ₹3,186.99 |
| Add 15% CPOH on "Y-A" | ₹5.64 |
| TOTAL | ₹3,192.63 |
| Add Cess @ 1% on "Z-A" | ₹0.43 |
| Cost of 10 holes | ₹3,193.06 |
| Cost of 1 hole | ₹319.31 |
| Say | ₹319.30 |