CPWD DSR item 2.30.2 rate analysis

Ordinary rock

Published rate₹194.25per hole
Rate analysis

Ordinary rock

DSR rate₹194.25per hole
Item code
2.30.2
Sub-head
SH 2 · EARTH WORK
Unit
hole
Source row
1800

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10 holes-
Earth work 10 x 0.3 (avg) = 3.0 cum
2.9.1 Rate as per Item Number 2.9.1 of SH: Earth Work cum 3 ₹632.95 ₹1,898.85
Extra labour for filling and ramming
9999 Sundries L.S. 13.52 ₹2.27 ₹30.69

Rate build-up

TOTAL ₹1,929.54
Add 1 % Water charges on "W-A" ₹0.31
TOTAL ₹1,929.85
Add GST on "X-A" (multiplying factor 0.2127) ₹6.59
TOTAL ₹1,936.44
Add 15% CPOH on "Y-A" ₹5.64
TOTAL ₹1,942.08
Add Cess @ 1% on "Z-A" ₹0.43
Cost of 10 holes ₹1,942.51
Cost of 1 hole ₹194.25
Say ₹194.25