Rate analysis
All kinds of soil
DSR rate₹82.45per hole
- Item code
- 2.30.1
- Sub-head
- SH 2 · EARTH WORK
- Unit
- hole
- Source row
- 1781
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 10 holes- | |||||
| Earth work 10 x 0.30 (avg) = 3.0 cum | |||||
| 2.8.1 | Rate as per item no. 2.8.1 of SH: Earth work | cum | 3 | ₹260.30 | ₹780.90 |
| Extra labour for filling and ramming | |||||
| 9999 | Sundries | L.S. | 13.52 | ₹2.27 | ₹30.69 |
Rate build-up
| TOTAL | ₹811.59 |
| Add 1 % Water charges on "W-A" | ₹0.31 |
| TOTAL | ₹811.90 |
| Add GST on "X-A" (multiplying factor 0.2127) | ₹6.59 |
| TOTAL | ₹818.49 |
| Add 15% CPOH on "Y-A" | ₹5.64 |
| TOTAL | ₹824.13 |
| Add Cess @ 1% on "Z-A" | ₹0.43 |
| Cost of 10 holes | ₹824.56 |
| Cost of 1 hole | ₹82.46 |