DSR 2023 · SH 2 · EARTH WORK

CPWD DSR item 2.30.1 rate analysis

All kinds of soil

Published rate₹82.45per hole
Rate analysis

All kinds of soil

DSR rate₹82.45per hole
Item code
2.30.1
Sub-head
SH 2 · EARTH WORK
Unit
hole
Source row
1781

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10 holes-
Earth work 10 x 0.30 (avg) = 3.0 cum
2.8.1 Rate as per item no. 2.8.1 of SH: Earth work cum 3 ₹260.30 ₹780.90
Extra labour for filling and ramming
9999 Sundries L.S. 13.52 ₹2.27 ₹30.69

Rate build-up

TOTAL ₹811.59
Add 1 % Water charges on "W-A" ₹0.31
TOTAL ₹811.90
Add GST on "X-A" (multiplying factor 0.2127) ₹6.59
TOTAL ₹818.49
Add 15% CPOH on "Y-A" ₹5.64
TOTAL ₹824.13
Add Cess @ 1% on "Z-A" ₹0.43
Cost of 10 holes ₹824.56
Cost of 1 hole ₹82.46
Say ₹82.45

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook