Rate analysis
Supplying and filling in plinth with sand under floors, including watering, ramming, consolidating and dressing complete.
DSR rate₹2,123.75per cum
- Item code
- 2.27
- Sub-head
- SH 2 · EARTH WORK
- Unit
- cum
- Source row
- 1720
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 10 cum. | |||||
| MATERIAL | |||||
| 6501 | Sand zone V (Jamuna) | cum | 10 | ₹1,320.00 | ₹13,200.00 |
| 2335 | Carriage of Jamuna sand | cum | 10 | ₹0.00 | ₹0.00 |
| LABOUR | |||||
| 0114 | Beldar | day | 0.89 | ₹736.00 | ₹655.04 |
| 0115 | Coolie | day | 1.07 | ₹736.00 | ₹787.52 |
| 0101 | Bhisti | day | 0.35 | ₹816.00 | ₹285.60 |
Rate build-up
| TOTAL | ₹14,928.16 |
| Add 1 % Water charges on "W" | ₹149.28 |
| TOTAL | ₹15,077.44 |
| Add GST on "X" (multiplying factor 0.2127) | ₹3,206.97 |
| TOTAL | ₹18,284.41 |
| Add 15% CPOH on "Y" | ₹2,742.66 |
| TOTAL | ₹21,027.07 |
| Add Cess @ 1% on "Z" | ₹210.27 |
| Cost of 10 cum. | ₹21,237.34 |
| Cost of 1 cum. | ₹2,123.73 |
| Say | ₹2,123.75 |