DSR 2023 · SH 2 · EARTH WORK

CPWD DSR item 2.28.1 rate analysis

Surface dressing of the ground including removing vegetation and in-equalities not exceeding 15 cm deep and disposal of rubbish, lead up to 50 m and lift up to 1.5 m. All kinds of soil

Published rate₹34.15per sqm
Rate analysis

Surface dressing of the ground including removing vegetation and in-equalities not exceeding 15 cm deep and disposal of rubbish, lead up to 50 m and lift up to 1.5 m.

DSR rate₹34.15per sqm

All kinds of soil

Item code
2.28.1
Sub-head
SH 2 · EARTH WORK
Unit
sqm
Source row
1742

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 100 sqm.
LABOUR
0114 Beldar day 1.97 ₹736.00 ₹1,449.92
0115 Coolie day 1.29 ₹736.00 ₹949.44

Rate build-up

TOTAL ₹2,399.36
Add 1 % Water charges on "W" ₹23.99
TOTAL ₹2,423.35
Add GST on "X" (multiplying factor 0.2127) ₹515.45
TOTAL ₹2,938.80
Add 15% CPOH on "Y" ₹440.82
TOTAL ₹3,379.62
Add Cess @ 1% on "Z" ₹33.80
Cost of 100 sqm. ₹3,413.42
Cost of 1 sqm. ₹34.13
Say ₹34.15

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook