DSR 2023 · SH 2 · EARTH WORK

CPWD DSR item 2.26.2 rate analysis

Extra for every additional lift of 1.5 m or part thereof in excavation / banking excavated or stacked materials. Ordinary or hard rock

Published rate₹227.40per cum
Rate analysis

Extra for every additional lift of 1.5 m or part thereof in excavation / banking excavated or stacked materials.

DSR rate₹227.40per cum

Ordinary or hard rock

Item code
2.26.2
Sub-head
SH 2 · EARTH WORK
Unit
cum
Source row
1683

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10 cum.
LABOUR
0128 Mate day 0.2 ₹816.00 ₹163.20
0114 Beldar day 1.95 ₹736.00 ₹1,435.20

Rate build-up

TOTAL ₹1,598.40
Add 1 % Water charges on "W" ₹15.98
TOTAL ₹1,614.38
Add GST on "X" (multiplying factor 0.2127) ₹343.38
TOTAL ₹1,957.76
Add 15% CPOH on "Y" ₹293.66
TOTAL ₹2,251.42
Add Cess @ 1% on "Z" ₹22.51
Cost of 10 cum. ₹2,273.93
Cost of 1 cum. ₹227.39
Say ₹227.40