Rate analysis
Extra for every additional lift of 1.5 m or part thereof in excavation / banking excavated or stacked materials.
DSR rate₹227.40per cum
Ordinary or hard rock
- Item code
- 2.26.2
- Sub-head
- SH 2 · EARTH WORK
- Unit
- cum
- Source row
- 1683
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 10 cum. | |||||
| LABOUR | |||||
| 0128 | Mate | day | 0.2 | ₹816.00 | ₹163.20 |
| 0114 | Beldar | day | 1.95 | ₹736.00 | ₹1,435.20 |
Rate build-up
| TOTAL | ₹1,598.40 |
| Add 1 % Water charges on "W" | ₹15.98 |
| TOTAL | ₹1,614.38 |
| Add GST on "X" (multiplying factor 0.2127) | ₹343.38 |
| TOTAL | ₹1,957.76 |
| Add 15% CPOH on "Y" | ₹293.66 |
| TOTAL | ₹2,251.42 |
| Add Cess @ 1% on "Z" | ₹22.51 |
| Cost of 10 cum. | ₹2,273.93 |
| Cost of 1 cum. | ₹227.39 |
| Say | ₹227.40 |