Rate analysis
Extra for every additional lift of 1.5 m or part thereof in excavation / banking excavated or stacked materials.
DSR rate₹126.80per cum
All kinds of soil
- Item code
- 2.26.1
- Sub-head
- SH 2 · EARTH WORK
- Unit
- cum
- Source row
- 1683
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 10 cum. | |||||
| LABOUR | |||||
| 0128 | Mate | day | 0.1 | ₹816.00 | ₹81.60 |
| 0114 | Beldar | day | 1.1 | ₹736.00 | ₹809.60 |
Rate build-up
| TOTAL | ₹891.20 |
| Add 1 % Water charges on "W" | ₹8.91 |
| TOTAL | ₹900.11 |
| Add GST on "X" (multiplying factor 0.2127) | ₹191.45 |
| TOTAL | ₹1,091.56 |
| Add 15% CPOH on "Y" | ₹163.73 |
| TOTAL | ₹1,255.29 |
| Add Cess @ 1% on "Z" | ₹12.55 |
| Cost of 10 cum. | ₹1,267.84 |
| Cost of 1 cum. | ₹126.78 |
| Say | ₹126.80 |