DSR 2023 · SH 2 · EARTH WORK

CPWD DSR item 2.26.1 rate analysis

Extra for every additional lift of 1.5 m or part thereof in excavation / banking excavated or stacked materials. All kinds of soil

Published rate₹126.80per cum
Rate analysis

Extra for every additional lift of 1.5 m or part thereof in excavation / banking excavated or stacked materials.

DSR rate₹126.80per cum

All kinds of soil

Item code
2.26.1
Sub-head
SH 2 · EARTH WORK
Unit
cum
Source row
1683

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10 cum.
LABOUR
0128 Mate day 0.1 ₹816.00 ₹81.60
0114 Beldar day 1.1 ₹736.00 ₹809.60

Rate build-up

TOTAL ₹891.20
Add 1 % Water charges on "W" ₹8.91
TOTAL ₹900.11
Add GST on "X" (multiplying factor 0.2127) ₹191.45
TOTAL ₹1,091.56
Add 15% CPOH on "Y" ₹163.73
TOTAL ₹1,255.29
Add Cess @ 1% on "Z" ₹12.55
Cost of 10 cum. ₹1,267.84
Cost of 1 cum. ₹126.78
Say ₹126.80

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook