DSR 2023 · SH 2 · EARTH WORK

CPWD DSR item 2.25 rate analysis

Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 and for all lift.

Published rate₹700.50per cum
Rate analysis

Filling available excavated earth (excluding rock) in trenches, plinth, sides of foundations etc. in layers not exceeding 20cm in depth, consolidating each deposited layer by ramming and watering, lead up to 50 and for all lift.

DSR rate₹700.50per cum
Item code
2.25
Sub-head
SH 2 · EARTH WORK
Unit
cum
Source row
1638

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10 cum.
LABOUR
0114 Beldar day 0.45 ₹736.00 ₹331.20
0115 Coolie day 1.208 ₹736.00 ₹889.09
0101 Bhisti day 0.18 ₹816.00 ₹146.88
9999 Sundries (Minor T&P) L.S. 4.61 ₹2.27 ₹10.46
2.25(a) Excavating, supplying, stacking and filling of local earth (including royalty) by mechanical transport upto a lead of 5km also including ramming and watering of the earth in layers not exceeding 20 cm in foundation trenches, plinth, sides of foundation etc. complete for all lift.
Details of cost for 10 cum
0020 Hydraulic Excavator (3D) with driver and fuel. (Cofficient from item no 2.6.1) day 0.08 ₹7,850.00 ₹628.00
LABOUR
0128 Mate day 0.04 ₹816.00 ₹32.64
0114 Beldar (1/2x0.89=0.45 day) day 0.45 ₹736.00 ₹331.20
0115 Coolie day 1.208 ₹736.00 ₹889.09
0101 Bhisti day 0.18 ₹816.00 ₹146.88
Carriage of materials upto 5 km
1.1.2 Rate as per item no 1.1.2 of SH:1 carriage of materials including loading, unloading and stacking cum 10 ₹326.68 ₹3,266.80
0979 Royalty for good earth cum 10 ₹60.00 ₹600.00

Rate build-up

TOTAL ₹1,377.63
Add 1 % Water charges on "W" ₹13.78
TOTAL ₹1,391.41
Add GST on "X" (multiplying factor 0.2127) ₹295.95
TOTAL ₹1,687.36
Add 15% CPOH on "Y" ₹253.10
TOTAL ₹1,940.46
Add Cess @ 1% on "Z" ₹19.40
Cost of 10 cum. ₹1,959.86
Cost of 1 cum. ₹195.99
Say ₹196.00
TOTAL ₹5,894.61
Add 1 % Water charges on "W-A" ₹26.28
TOTAL ₹5,920.89
Add GST on "X-A" (multiplying factor 0.2127) ₹564.52
TOTAL ₹6,485.41
Add 15% CPOH on "Y-A" ₹482.79
TOTAL ₹6,968.20
Add Cess @ 1% on "Z-A" ₹37.01
Cost of 10 cum ₹7,005.21
Cost of 1 cum ₹700.52
Say ₹700.50