DSR 2023 · SH 2 · EARTH WORK

CPWD DSR item 2.24.2 rate analysis

Extra rates for quantities of works, executed: In or under foul position, including pumping out water as required

Published rate₹0.25per metre depth
Rate analysis

Extra rates for quantities of works, executed:

DSR rate₹0.25per metre depth

In or under foul position, including pumping out water as required

Item code
2.24.2
Sub-head
SH 2 · EARTH WORK
Unit
metre depth
Source row
1623

Cost components

CodeDescriptionUnitQuantityRateAmount
Extra due to slow progress and dewatering: 25% of the rate of the item metre depth
Note for item no. 2.24:- The extra percentage rate is applicable in respect of each item but limited to quantities of work executed in these difficult conditions. The unit, namely, metre depth, to be considered for payment, shall be the depth measured from the sub soil water level up to the centre of gravity of the qty executed in difficult conditions. The depth shall be reckoned correct to 0.10 m, 0.05 m or more shall be taken as 0.10 m and less than 0.05 m ignored.

Rate build-up

Cost of 1 metre depth ₹0.25
Say ₹0.25

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook