DSR 2023 · SH 2 · EARTH WORK

CPWD DSR item 2.24.1 rate analysis

Extra rates for quantities of works, executed: In or under water and/or liquid mud, including pumping out water as required

Published rate₹0.20per metre depth
Rate analysis

Extra rates for quantities of works, executed:

DSR rate₹0.20per metre depth

In or under water and/or liquid mud, including pumping out water as required

Item code
2.24.1
Sub-head
SH 2 · EARTH WORK
Unit
metre depth
Source row
1623

Cost components

CodeDescriptionUnitQuantityRateAmount
Extra due to slow progress and dewatering: 20% of the rate of the item metre depth

Rate build-up

Cost of 1 metre depth ₹0.20
Say ₹0.20