DSR 2023 · SH 2 · EARTH WORK

CPWD DSR item 2.20.1 rate analysis

Depth not exceeding 1.5 m

Published rate₹72.05per sqm
Rate analysis

Depth not exceeding 1.5 m

DSR rate₹72.05per sqm
Item code
2.20.1
Sub-head
SH 2 · EARTH WORK
Unit
sqm
Source row
1206

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for a trench of length 30m and 1.50m deep
surface area - 2x30x1.5 = 90 sqm.
MATERIAL
The Material can be used four times on the same work and after use of material credit is given @ 75% of cost
Poling board of
1198 Second class kail wood in planks 10 cudm 7.125 ₹260.00 ₹1,852.50
1.5mx0.25x0.038m
2x40x1.5x0.25x0.038= 1.14cum = 1140 cudm
Qty taken for cost of using once after
deducting for credit = 1140x¼x¼ = 71.25 cudm
1197 Second class kail wood in scantling 10 cudm 7.5 ₹260.00 ₹1,950.00
Walling l00mmxl00mm : 4x30mx0.l0mx0.l0m = 1.20cum= 1200 cudm
Qty taken for cost of using once after
deducting for credit = 1200x¼x¼ = 75 dm³
Struts of
0302 Safeda ballies 125 mm diameter metre 3.18 ₹44.00 ₹139.92
and 1.5m long
2x17x1.50 = 51m
Qty taken for cost of using once after
deducting for credit = 51x¼x¼ = 3.18 m
2204 Carriage of Timber cum 0.74 ₹0.00 ₹0.00
CARRIAGE:
Poling boards = 1.14 cum
Walling = 1.20 cum
Ballies struts 3.14/4x(0.125) ² = 0.63 cum
Total of carriage = 2.97 cum x ¼ = 0.74
LABOUR
0112 Carpenter 2nd class day 0.25 ₹816.00 ₹204.00
0114 Beldar day 0.5 ₹736.00 ₹368.00
9999 Sundries L.S. 19.76 ₹2.27 ₹44.86

Rate build-up

TOTAL ₹4,559.28
Add 1 % Water charges on "W" ₹45.59
TOTAL ₹4,604.87
Add GST on "X" (multiplying factor 0.2127) ₹979.46
TOTAL ₹5,584.33
Add 15% CPOH on "Y" ₹837.65
TOTAL ₹6,421.98
Add Cess @ 1% on "Z" ₹64.22
Cost of 90 Sqm ₹6,486.20
Cost per sqm. ₹72.07
Say ₹72.05

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.