DSR 2023 · SH 2 · EARTH WORK

CPWD DSR item 2.20.2 rate analysis

Depth exceeding 1.5 m but not exceeding 3 m

Published rate₹81.60per sqm
Rate analysis

Depth exceeding 1.5 m but not exceeding 3 m

DSR rate₹81.60per sqm
Item code
2.20.2
Sub-head
SH 2 · EARTH WORK
Unit
sqm
Source row
1250

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for a trench of length 30m and 1.5m deep
surface area - 2x30x1.5 = 90 sqm.
MATERIAL
The Material can be used four times on the same work and after use of material credit is given @ 75% of cost
Poling boards of
1198 Second class kail wood in planks 10 cudm 7.125 ₹260.00 ₹1,852.50
1.50mx0.25x0.038m 2x40x1.50x0.25x0.038= 1.14cum= 1140 cudm
Qty taken for cost of using once after
deducting for credit = 1140x¼x¼ = 71.25 dm³
Wallings of
1197 Second class kail wood in scantling 10 cudm 7.5 ₹260.00 ₹1,950.00
100mmx 100mm: 4x30mx0.l0mx0.l0m = 1.20cum= 1200 cudm
Qty taken for cost of using once after
deducting for credit = 1200x¼x¼ = 75 dm³
Struts of
0302 Safeda ballies 125 mm diameter metre 3.18 ₹44.00 ₹139.92
and 1.5m long
2x17x1.5 = 51m
Qty taken for cost of using once after
deducting for credit = 51x¼x¼ = 3.18 m
2204 Carriage of Timber cum 0.74 ₹0.00 ₹0.00
CARRIAGE:
Poling boards = 1.14 cum
Walling
Ballies struts 3.14/4x(0.125) ² = 0.63 cum
Total of carriage = 2.97 cum x ¼ = 0.74
LABOUR
0112 Carpenter 2nd class day 0.5 ₹816.00 ₹408.00
0114 Beldar day 1 ₹736.00 ₹736.00
9999 Sundries L.S. 33.15 ₹2.27 ₹75.25

Rate build-up

TOTAL ₹5,161.67
Add 1 % Water charges on "W" ₹51.62
TOTAL ₹5,213.29
Add GST on "X" (multiplying factor 0.2127) ₹1,108.87
TOTAL ₹6,322.16
Add 15% CPOH on "Y" ₹948.32
TOTAL ₹7,270.48
Add Cess @ 1% on "Z" ₹72.70
Cost of 90 Sqm ₹7,343.18
Cost per sqm. ₹81.59
Say ₹81.60