DSR 2023 · SH 2 · EARTH WORK

CPWD DSR item 2.19 rate analysis

Extra for planking, strutting and packing materials for cavities (in close timbering) if required to be left permanently in position. (Face area of timber permanently left to be measured).

Published rate₹1,692.45per sqm
Rate analysis

Extra for planking, strutting and packing materials for cavities (in close timbering) if required to be left permanently in position. (Face area of timber permanently left to be measured).

DSR rate₹1,692.45per sqm
Item code
2.19
Sub-head
SH 2 · EARTH WORK
Unit
sqm
Source row
1170

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for a trench 30m long and 1.5m deep
area 2x30x1.5=90 sqm-
MATERIAL
Poling boards of
1198 Second class kail wood in planks 10 cudm 299.25 ₹260.00 ₹77,805.00
90x0.038 = 3.42 cum = 3420 cudm
Less @ 1/8 of Qty as timber is supposed to be used once before = 3420 - 427.5 = 2992.5 dm ³
Walings 100mmx100mm of
1197 Second class kail wood in scantling 10 cudm 105 ₹260.00 ₹27,300.00
4x30x0.10x0.10 = 1.20cum = 1200 cudm
Less @ 1/8 of Qty as timber is supposed to be used once before = 1200 - 150 = 1050 dm ³
Struts of
0302 Safeda ballies 125 mm diameter metre 44.63 ₹44.00 ₹1,963.72
and 1.5m long
2x17x1.5 = 51m
Less @ 1/8 of Qty as timber is supposed to be used once before = 51 - 6.37 = 44.63 m
2204 Carriage of Timber cum 2.675 ₹0.00 ₹0.00
Poling boards = 3.42 cum
Walling= 1.20 cum.
Balli struts: 3.14/4x(0.125) ² x 51 = 0.63 cum
= 5.25 cum Taking half = 5.25 x ½ = 2.675 cum

Rate build-up

TOTAL ₹1,07,068.72
Add 1 % Water charges on "W" ₹1,070.69
TOTAL ₹1,08,139.41
Add GST on "X" (multiplying factor 0.2127) ₹23,001.25
TOTAL ₹1,31,140.66
Add 15% CPOH on "Y" ₹19,671.10
TOTAL ₹1,50,811.76
Add Cess @ 1% on "Z" ₹1,508.12
Cost of 90 Sqm. ₹1,52,319.88
Cost per sqm. ₹1,692.44
Say ₹1,692.45