DSR 2023 · SH 2 · EARTH WORK

CPWD DSR item 2.14.2.1 rate analysis

Extra for excavating trenches for pipes, cables, etc. in ordinary/hard rock exceeding 1.5 m in depth but not exceeding 3 m. (Rate is over corresponding basic item for depth upto 1.5 metre) Hard rock (requiring blasting) Pipes, cables etc. exceeding 80 mm dia but not exceeding 300 mm dia

Published rate₹1,091.45DSR 2023
Rate analysis

Extra for excavating trenches for pipes, cables, etc. in ordinary/hard rock exceeding 1.5 m in depth but not exceeding 3 m. (Rate is over corresponding basic item for depth upto 1.5 metre) Hard rock (requiring blasting)

DSR rate₹1,091.45as per item analysis

Pipes, cables etc. exceeding 80 mm dia but not exceeding 300 mm dia

Item code
2.14.2.1
Sub-head
SH 2 · EARTH WORK
Unit
See analysis
Source row
581

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 300m length of a pipe of an average dia. say 200mm.
Slope assumed 1 in 200.
Excavation-
100x0.90x1.75 = 157.50 cum.
200x0.90x(2.00 +3.00)/2= 450 cum.
Total = 607.50 cum.
2.9.2 Rate as per item no. 2.9.2 of SH: Earth Work cum 607.5 ₹1,049.80 ₹6,37,753.50
Refilling, ramming and watering = 607.50 cum
2.25 Rate as per item No.2.25 of SH: Earth Work cum 607.5 ₹196.00 ₹1,19,070.00
Extra labour for ramming of rock=(2.75 * 607.5/93.60 = 17.85)(Based on Item No 2.13.2.2)
0114 Beldar day 17.85 ₹736.00 ₹13,137.60
2.13.2.2 Less excavation for depth upto 1.50 m Rate as per Item No.2.13.2.2 of SH: Earth Work metre -300 ₹1,493.60 -₹4,48,080.00
Extra cost for one metre length ₹1,091.45

Rate build-up

TOTAL ₹3,21,881.10
Add 1 % Water charges on "W-A" ₹131.38
TOTAL ₹3,22,012.48
Add GST on "X-A" (multiplying factor 0.2127) ₹2,822.31
TOTAL ₹3,24,834.79
Add 15% CPOH on "Y-A" ₹2,413.69
TOTAL ₹3,27,248.48
Add Cess @ 1% on "Z-A" ₹185.05
Cost for 300m length of pipe ₹3,27,433.53
Say ₹1,091.45

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook