DSR 2023 · SH 2 · EARTH WORK

CPWD DSR item 2.14.1.2 rate analysis

Extra for excavating trenches for pipes, cables, etc. in ordinary/hard rock exceeding 1.5 m in depth but not exceeding 3 m. (Rate is over corresponding basic item for depth upto 1.5 metre) Ordinary rock : Pipes, cables exceeding 300 mm dia but not exceeding 600 mm dia

Published rate₹867.45DSR 2023
Rate analysis

Extra for excavating trenches for pipes, cables, etc. in ordinary/hard rock exceeding 1.5 m in depth but not exceeding 3 m. (Rate is over corresponding basic item for depth upto 1.5 metre) Ordinary rock :

DSR rate₹867.45as per item analysis

Pipes, cables exceeding 300 mm dia but not exceeding 600 mm dia

Item code
2.14.1.2
Sub-head
SH 2 · EARTH WORK
Unit
See analysis
Source row
581

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 300m length of a pipe of an average dia. say 450mm.
Slope assumed 1 in 200.
Excavation-
100x1.05x1.75 = 183.75 cum.
200x1.05x(2.00 +3.00)/2= 525.00 cum.
Total = 708.75 cum.
2.9.1 Rate as per item no. 2.9.1 of SH: Earth Work cum 708.75 ₹632.95 ₹4,48,603.31
Refilling, ramming and watering = 708.75 cum
2.25 Rate as per item No.2.25 of SH: Earth Work cum 708.75 ₹196.00 ₹1,38,915.00
Extra labour for ramming of rock=(2.20 * 708.75/93.60 = 19.04)(Based on Item No 2.13.1.2)
0114 Beldar day 16.66 ₹736.00 ₹12,261.76
2.13.1.3 Less excavation for depth upto 1.50 m Rate as per Item No.2.13.1.3 of SH: Earth Work metre -300 ₹1,149.10 -₹3,44,730.00
Extra cost for one metre length ₹867.44

Rate build-up

TOTAL ₹2,55,050.07
Add 1 % Water charges on "W-A" ₹122.62
TOTAL ₹2,55,172.69
Add GST on "X-A" (multiplying factor 0.2127) ₹2,634.16
TOTAL ₹2,57,806.85
Add 15% CPOH on "Y-A" ₹2,252.78
TOTAL ₹2,60,059.63
Add Cess @ 1% on "Z-A" ₹172.71
Cost for 300m length of pipe ₹2,60,232.34
Say ₹867.45

Use this rate in the interactive workbook