DSR 2023 · SH 2 · EARTH WORK

CPWD DSR item 2.14.2.2 rate analysis

Extra for excavating trenches for pipes, cables, etc. in ordinary/hard rock exceeding 1.5 m in depth but not exceeding 3 m. (Rate is over corresponding basic item for depth upto 1.5 metre) Hard rock (requiring blasting) Pipes, cables exceeding 300 mm dia but not exceeding 600 mm dia

Published rate₹1,297.40DSR 2023
Rate analysis

Extra for excavating trenches for pipes, cables, etc. in ordinary/hard rock exceeding 1.5 m in depth but not exceeding 3 m. (Rate is over corresponding basic item for depth upto 1.5 metre) Hard rock (requiring blasting)

DSR rate₹1,297.40as per item analysis

Pipes, cables exceeding 300 mm dia but not exceeding 600 mm dia

Item code
2.14.2.2
Sub-head
SH 2 · EARTH WORK
Unit
See analysis
Source row
581

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 300m length of a pipe of an average dia. say 450mm.
Slope assumed 1 in 200.
Excavation-
100x1.05x1.75 = 183.75 cum.
200x1.05x(2.00 +3.00)/2= 525.00 cum.
Total = 708.75 cum.
2.9.2 Rate as per item no. 2.9.2 of SH: Earth Work cum 708.75 ₹1,049.80 ₹7,44,045.75
Refilling, ramming and watering = 708.75 cum
2.25 Rate as per item No.2.25 of SH: Earth Work cum 708.75 ₹196.00 ₹1,38,915.00
Extra labour for ramming of rock=(2.75 * 708.75/93.60 = 20.82)(Based on Item No 2.13.2.2)
0114 Beldar day 20.82 ₹736.00 ₹15,323.52
2.13.2.3 Less excavation for depth upto 1.50 m Rate as per Item No.2.13.2.3 of SH: Earth Work metre -300 ₹1,718.45 -₹5,15,535.00
Extra cost for one metre length ₹1,297.42

Rate build-up

TOTAL ₹3,82,749.27
Add 1 % Water charges on "W-A" ₹153.24
TOTAL ₹3,82,902.51
Add GST on "X-A" (multiplying factor 0.2127) ₹3,291.91
TOTAL ₹3,86,194.42
Add 15% CPOH on "Y-A" ₹2,815.30
TOTAL ₹3,89,009.72
Add Cess @ 1% on "Z-A" ₹215.84
Cost for 300m length of pipe ₹3,89,225.56
Say ₹1,297.40

Use this rate in the interactive workbook