Rate analysis
All kinds of soil
DSR rate₹352.15as per item analysis
Pipes, cables etc. exceeding 80 mm dia. but not exceeding 300 mm dia
- Item code
- 2.10.1.2
- Sub-head
- SH 2 · EARTH WORK
- Unit
- See analysis
- Source row
- 316
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 110m length of a pipe of an average dia. say 200mm. Slope assumed 1 in 200. | |||||
| Earth work and filling- Minimum depth of trench = 0.75+0.20 = 0.95m, Average depth = (1.50+0.95)/2 = 1.225m, Width = 0.40 + 0.20 = 0.60 m, 110x0.60x1.225 = 80.85 cum, 5% for collars = 4.04 cum, Total = 84.89 cum | |||||
| 2.8.1 | Rate as per item no. 2.8.1 of SH: Earth work | cum | 84.89 | ₹260.30 | ₹22,096.87 |
| 2.25 | Rate as per Item Number 2.25 of | — | — | — | — |
| — | SH: Earth Work | cum | 84.89 | ₹196.00 | ₹16,638.44 |
Rate build-up
| TOTAL | ₹38,735.31 |
| Cost of 110m length of pipe | ₹38,735.31 |
| Cost for 1m length of pipe | ₹352.14 |
| Say | ₹352.15 |