DSR 2023 · SH 2 · EARTH WORK

CPWD DSR item 2.10.1.1 rate analysis

All kinds of soil Pipes, cables etc, not exceeding 80 mm dia.

Published rate₹215.60DSR 2023
Rate analysis

All kinds of soil

DSR rate₹215.60as per item analysis

Pipes, cables etc, not exceeding 80 mm dia.

Item code
2.10.1.1
Sub-head
SH 2 · EARTH WORK
Unit
See analysis
Source row
316

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 180m length of a pipe of an average dia. say 40mm. Slope assumed 1 in 200.
Earth work and filling-
Minimum depth of trench 60cm. Average depth = (0.6+1.5)/2 = 1.05, Width for this depth 0.45 cm, 180x0.45x1.05 = 85.05 cum
2.8.1 Rate as per item no. 2.8.1 of SH: Earth work cum 85.05 ₹260.30 ₹22,138.52
2.25 Rate as per Item Number 2.25 of
SH: Earth Work cum 85.05 ₹196.00 ₹16,669.80

Rate build-up

TOTAL ₹38,808.32
Cost of 180m length of pipes ₹38,808.32
Cost for 1m. length of pipe ₹215.60
Say ₹215.60