Rate analysis
All kinds of soil
DSR rate₹549.75as per item analysis
Pipes, cables etc. exceeding 300 mm dia but not exceeding 600 mm
- Item code
- 2.10.1.3
- Sub-head
- SH 2 · EARTH WORK
- Unit
- See analysis
- Source row
- 316
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 60m length of a pipe of an average dia. say 450mm. Slope assumed 1 in 200. | |||||
| Earth work and filling- Minimum depth of trench 0.75+0.45= 1.20m, Average depth = (1.50+1.20)/2 = 1.35, Width = 0.40 + 0.45 = 0.85 m, 60x0.85x1.35 = 68.85 cum, 5% for collars = 3.44 cum, Total = 72.29 cum | |||||
| 2.8.1 | Rate as per item no. 2.8.1 of SH: Earth work | cum | 72.29 | ₹260.30 | ₹18,817.09 |
| 2.25 | Rate as per Item Number 2.25 of | — | — | — | — |
| — | SH: Earth Work | cum | 72.29 | ₹196.00 | ₹14,168.84 |
Rate build-up
| TOTAL | ₹32,985.93 |
| Cost of 60m length of pipe | ₹32,985.93 |
| Cost for 1m length of pipe | ₹549.77 |
| Say | ₹549.75 |