CPWD DSR item 9.54.1 rate analysis

Providing beams including hoisting, fixing in position and applying wood preservative for the unexposed surfaces, etc. complete with : Sal wood

Published rate₹1,03,140.10per cum
Rate analysis

Providing beams including hoisting, fixing in position and applying wood preservative for the unexposed surfaces, etc. complete with :

DSR rate₹1,03,140.10per cum

Sal wood

Item code
9.54.1
Sub-head
SH 9 · WOOD & PVC WORK
Unit
cum
Source row
3001

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for a beam 450x30x15cm = 0.203cum. or 203cudm.
MATERIAL
Sal wood = 203 cudm.+
Add wastage @ 2% = 4.06cudm.
Total = 207.06cudm. Say 207.1 cudm.
1199 Sal wood in scantling 10 cudm 20.71 ₹600.00 ₹12,426.00
2204 Carriage of Timber cum 0.2071 ₹0.00 ₹0.00
Priming coat (wood preservative)
13.57.1 Rate as per item no 13.57.1 SH : Finishing sqm 0.54 ₹54.40 ₹29.38
LABOUR
0112 Carpenter 2nd class day 0.7 ₹816.00 ₹571.20
0114 Beldar day 1.45 ₹736.00 ₹1,067.20
0100 Bandhani day 0.7 ₹816.00 ₹571.20
9999 Sundries L.S. 26.91 ₹2.27 ₹61.09

Rate build-up

TOTAL ₹14,726.07
Add 1 % Water charges on "W-A" ₹146.97
TOTAL ₹14,873.04
Add GST on "X-A" (multiplying factor 0.2127) ₹3,157.25
TOTAL ₹18,030.29
Add 15% CPOH on "Y-A" ₹2,700.14
TOTAL ₹20,730.43
Add Cess @ 1% on "Z-A" ₹207.01
Cost for 203 cudm. ₹20,937.44
Cost of 1 cum. ₹1,03,140.10
Say ₹1,03,140.10