DSR 2023 · SH 9 · WOOD & PVC WORK

CPWD DSR item 9.54.2 rate analysis

Providing beams including hoisting, fixing in position and applying wood preservative for the unexposed surfaces, etc. complete with : Hollock wood

Published rate₹69,178.05per cum
Rate analysis

Providing beams including hoisting, fixing in position and applying wood preservative for the unexposed surfaces, etc. complete with :

DSR rate₹69,178.05per cum

Hollock wood

Item code
9.54.2
Sub-head
SH 9 · WOOD & PVC WORK
Unit
cum
Source row
3001

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for a beam 450x30x15cm = 0.203cum. or 203cudm.
MATERIAL
Hollock wood = 203 cudm.+
Add wastage @ 2% = 4.06cudm.
Total = 207.06cudm. Say 207.1 cudm.
2466 Hollock wood in scantling 10 cudm 20.71 ₹366.00 ₹7,579.86
2204 Carriage of Timber cum 0.207 ₹0.00 ₹0.00
Priming coat (wood preservative)
13.57.1 Rate as per item no 13.57.1 SH : Finishing sqm 0.54 ₹54.40 ₹29.38
LABOUR
0112 Carpenter 2nd class day 0.7 ₹816.00 ₹571.20
0114 Beldar day 1.45 ₹736.00 ₹1,067.20
0100 Bandhani day 0.7 ₹816.00 ₹571.20
9999 Sundries L.S. 26.91 ₹2.27 ₹61.09

Rate build-up

TOTAL ₹9,879.93
Add 1 % Water charges on "W-A" ₹98.51
TOTAL ₹9,978.44
Add GST on "X-A" (multiplying factor 0.2127) ₹2,116.17
TOTAL ₹12,094.61
Add 15% CPOH on "Y-A" ₹1,809.78
TOTAL ₹13,904.39
Add Cess @ 1% on "Z-A" ₹138.75
Cost for 203 cudm. ₹14,043.14
Cost of 1 cum. ₹69,178.03
Say ₹69,178.05