Rate analysis
Providing 40x5 mm flat iron hold fast 400 mm long including fixing to frame with 10 mm diameter bolts, nuts and wooden plugs and embedding in cement concrete block 300x100x150mm 1:3:6 mix (1 cement : 3 coarse sand : 6 graded stone aggregate 20mm nominal size).
DSR rate₹226.55as per item analysis
- Item code
- 9.53
- Sub-head
- SH 9 · WOOD & PVC WORK
- Unit
- See analysis
- Source row
- 2973
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 1 hold fast | |||||
| MATERIAL | |||||
| M.S.flat 40x5mm 40cm long @ 1.68 kg/m = 0.672 kg = 0.0067 qunital | |||||
| 1008 | Flats upto 10 mm in thickness | quintal | 0.0067 | ₹5,450.00 | ₹36.52 |
| 9977 | Carriage of steel | L.S. | 1.82 | ₹2.27 | ₹4.13 |
| Cement concrete 1:3:6 | |||||
| 30x10x15cm= 0.0045cum.+ | |||||
| Add wastage @ 10% = 0.00045cum. | |||||
| Total = 0.00495cum. Say 0.005cum. | |||||
| 4.2.5 | Rate as per item no 4.2.5 of SH : Concrete work | cum | 0.005 | ₹9,311.40 | ₹46.56 |
| 9999 | Bolts and nuts | L.S. | 5.46 | ₹2.27 | ₹12.39 |
| LABOUR | |||||
| 0103 | Blacksmith 2nd class | day | 0.03 | ₹816.00 | ₹24.48 |
| 0123 | Mason (brick layer) 1st class | day | 0.03 | ₹897.00 | ₹26.91 |
| 0114 | Beldar | day | 0.03 | ₹736.00 | ₹22.08 |
Rate build-up
| TOTAL | ₹173.07 |
| Add 1 % Water charges on "W-A" | ₹1.27 |
| TOTAL | ₹174.34 |
| Add GST on "X-A" (multiplying factor 0.2127) | ₹27.18 |
| TOTAL | ₹201.52 |
| Add 15% CPOH on "Y-A" | ₹23.24 |
| TOTAL | ₹224.76 |
| Add Cess @ 1% on "Z-A" | ₹1.78 |
| Cost for 1 no | ₹226.54 |
| Say | ₹226.55 |