Rate analysis
Providing and fixing adjustable stainless steel cramps of approved quality, required shape and size, adjustable with stainless steel nuts, bolts and washer (total weight not less than 260 gms), for dry stone cladding fixed on frame work at suitable location, including making necessary recesses in stone slab, drilling required holes etc complete as per direction of the Engineer-in-charge.
DSR rate₹437.00as per item analysis
- Item code
- 8.22
- Sub-head
- SH 8 · CLADDING WORK
- Unit
- See analysis
- Source row
- 1683
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 10 Nos. | |||||
| 8698 | Stainless steel cramps(weight 260 grams) with nuts, bolts and washer for dry stone cladding | each | 10 | ₹127.00 | ₹1,270.00 |
| LABOUR | |||||
| For making holes, recesses etc. and fixing of stainless steel cramps. | |||||
| 0103 | Blacksmith 2nd class | day | 0.1 | ₹816.00 | ₹81.60 |
| 0124 | Mason 2nd class | day | 1 | ₹816.00 | ₹816.00 |
| 0114 | Beldar | day | 1.1 | ₹736.00 | ₹809.60 |
| 9999 | Scaffolding, hire charges of drill machine etc. | L.S. | 20.8 | ₹2.27 | ₹47.22 |
| 9999 | Sundries | L.S. | 20.8 | ₹2.27 | ₹47.22 |
Rate build-up
| TOTAL | ₹3,071.64 |
| Add 1 % Water charges on "W" | ₹30.72 |
| TOTAL | ₹3,102.36 |
| Add GST on "X" (multiplying factor 0.2127) | ₹659.87 |
| TOTAL | ₹3,762.23 |
| Add 15% CPOH on "Y" | ₹564.33 |
| TOTAL | ₹4,326.56 |
| Add Cess @ 1% on "Z" | ₹43.27 |
| Cost for 10 Nos. | ₹4,369.83 |
| Cost for 1 Nos. | ₹436.98 |
| Say | ₹437.00 |