Providing and fixing structural steel frame (for dry cladding with 30 mm thick gang saw cut with machine cut edges sand stone) on walls at all heights using M.S. square/ rectangular tube in the required pattern as per architectural drawing, including cost of cutting, bending, welding etc. The frame work shall be fixed to the wall with the help of M.S. brackets/ lugs of angle iron/ flats etc. which shall be welded to the frame and embedded in brick wall with cement concrete block 1:2:4 (1 cement :2 coarse sand :4 graded stone aggregate 20 mm nominal size) of size 300x230x300 mm, including cost of necessary centring and shuttering and with approved expansion hold fasteners on CC/RCC surface, including drilling necessary holes. Approved cramps/ pins etc. shall be welded to the frame work to support stone cladding, the steel work will be given a priming coat of Zinc primer as approved by Engineer-in-charge and painted with two or more coats of epoxy paint (Shop drawings shall be submitted by the contractor to the Engineer-in-charge for approval before execution). The frame work shall be fixed in true horizontal & vertical lines/planes. (Only structural steel frame work shall be measured for the purpose of payment, stainless steel cramps shall be paid for separately and nothing extra shall be paid).
Published rate₹269.95DSR 2023
Rate analysis
Providing and fixing structural steel frame (for dry cladding with 30 mm thick gang saw cut with machine cut edges sand stone) on walls at all heights using M.S. square/ rectangular tube in the required pattern as per architectural drawing, including cost of cutting, bending, welding etc. The frame work shall be fixed to the wall with the help of M.S. brackets/ lugs of angle iron/ flats etc. which shall be welded to the frame and embedded in brick wall with cement concrete block 1:2:4 (1 cement :2 coarse sand :4 graded stone aggregate 20 mm nominal size) of size 300x230x300 mm, including cost of necessary centring and shuttering and with approved expansion hold fasteners on CC/RCC surface, including drilling necessary holes. Approved cramps/ pins etc. shall be welded to the frame work to support stone cladding, the steel work will be given a priming coat of Zinc primer as approved by Engineer-in-charge and painted with two or more coats of epoxy paint (Shop drawings shall be submitted by the contractor to the Engineer-in-charge for approval before execution). The frame work shall be fixed in true horizontal & vertical lines/planes. (Only structural steel frame work shall be measured for the purpose of payment, stainless steel cramps shall be paid for separately and nothing extra shall be paid).
DSR rate₹269.95as per item analysis
Item code
8.21
Sub-head
SH 8 · CLADDING WORK
Unit
See analysis
Source row
1631
Cost components
Code
Description
Unit
Quantity
Rate
Amount
Details of cost for 100.78 kg.
M.S. tube 50x25x18mm
Vertical 4.0x3.0 mtr = 12.00
Vertical 4.0x3.0x0.93 =11.16 m
Total = 23.16 mtr
Add 10% wastage = 2.32 m
Total 25.48mtr @ 2.02 kg/m = 51.47 kg
4009
Mild steel tubes hot finished welded type
kilogram
51.47
₹72.00
₹3,705.84
Angle iron 50x50x6mm
16x0.60=9.60
16x0.15=2.40
Total=12.00
Add 10% wastage = 1.20m
Total=13.20m @4.50kg/m=59.40kg or 0.594 q
1007
Structurals such as tees,angles channels and R.S. joists
quintal
0.594
₹5,965.00
₹3,543.21
Cement concrete 1:2:4 =16x0.30x0.23x0.30=0.331 cum
4.1.3
Rate as per item no. 4.1.3 of SH : concrete work
cum
0.331
₹7,878.50
₹2,607.78
Making holes in brick work=16nos.
LABOUR
0123
Mason 1st class
day
0.26
₹897.00
₹233.22
0124
Mason 2nd class
day
0.26
₹816.00
₹212.16
0114
Beldar
day
2
₹736.00
₹1,472.00
Welding for frame welding
16x(2.5+5+2.5+5) = 240 cm
For hold fast 16x20cm = 320cm
Total = 560cm
1215
Welding by electric plant
cm
560
₹2.50
₹1,400.00
LABOUR
0102
Blacksmith 1st class
day
1.34
₹897.00
₹1,201.98
0100
Bandhani
day
0.67
₹816.00
₹546.72
0114
Beldar
day
4.92
₹736.00
₹3,621.12
9999
Sundries
L.S.
80.73
₹2.27
₹183.26
Painting with epoxy paint over and including
priming coat area 22.80x0.15 = 3.42
12x0.2 = 2.40
Total = 5.82sqm
13.52.1
Rate as per Item no. 13.52.1 of SH: Finishing
sqm
5.82
₹241.75
₹1,406.99
9999
For labour scaffocaling etc
L.S.
80.73
₹2.27
₹183.26
Rate build-up
TOTAL
₹20,317.54
Add 1 % Water charges on "W-A"
₹163.03
TOTAL
₹20,480.57
Add GST on "X-A" (multiplying factor 0.2127)
₹3,502.28
TOTAL
₹23,982.85
Add 15% CPOH on "Y-A"
₹2,995.21
TOTAL
₹26,978.06
Add Cess @ 1% on "Z-A"
₹229.63
Cost for 100.78 kg
₹27,207.69
Cost for 1 kg
₹269.97
Say
₹269.95