Rate analysis
Extra for random rubble masonry with hard stone in :
DSR rate₹2,530.60per cum
Circular pillars
- Item code
- 7.4.2
- Sub-head
- SH 7 · STONE WORK
- Unit
- cum
- Source row
- 68
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 1 cum | |||||
| 1157 | Stone for masonry work | cum | 0.29 | ₹1,250.00 | ₹362.50 |
| 2215 | Carriage of Soling stone & masonry stone | cum | 0.29 | ₹0.00 | ₹0.00 |
| LABOUR | |||||
| Labour for cutting and dressing stones- | |||||
| 0125 | Mason (for plain stone work) 2nd class) | day | 1.42 | ₹816.00 | ₹1,158.72 |
| 0115 | Coolie | day | 0.35 | ₹736.00 | ₹257.60 |
Rate build-up
| TOTAL | ₹1,778.82 |
| Add 1 % Water charges on "W" | ₹17.79 |
| TOTAL | ₹1,796.61 |
| Add GST on "X" (multiplying factor 0.2127) | ₹382.14 |
| TOTAL | ₹2,178.75 |
| Add 15% CPOH on "Y" | ₹326.81 |
| TOTAL | ₹2,505.56 |
| Add Cess @ 1% on "Z" | ₹25.06 |
| Cost of 1 cum | ₹2,530.62 |
| Say | ₹2,530.60 |