Rate analysis
Extra for random rubble masonry with hard stone curved on plan for a mean radius not exceeding 6 m.
DSR rate₹1,046.20per cum
- Item code
- 7.5
- Sub-head
- SH 7 · STONE WORK
- Unit
- cum
- Source row
- 106
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 1 cum | |||||
| 1157 | Stone for masonry work | cum | 0.1 | ₹1,250.00 | ₹125.00 |
| 2215 | Carriage of Soling stone & masonry stone | cum | 0.1 | ₹0.00 | ₹0.00 |
| LABOUR | |||||
| Labour for cutting and dressing stones- | |||||
| 0125 | Mason (for plain stone work) 2nd class) | day | 0.27 | ₹816.00 | ₹220.32 |
| 0115 | Coolie | day | 0.53 | ₹736.00 | ₹390.08 |
Rate build-up
| TOTAL | ₹735.40 |
| Add 1 % Water charges on "W" | ₹7.35 |
| TOTAL | ₹742.75 |
| Add GST on "X" (multiplying factor 0.2127) | ₹157.98 |
| TOTAL | ₹900.73 |
| Add 15% CPOH on "Y" | ₹135.11 |
| TOTAL | ₹1,035.84 |
| Add Cess @ 1% on "Z" | ₹10.36 |
| Cost of 1 cum. | ₹1,046.20 |
| Say | ₹1,046.20 |