Rate analysis
Extra for random rubble masonry with hard stone in :
DSR rate₹956.00per cum
Square or rectangular pillars
- Item code
- 7.4.1
- Sub-head
- SH 7 · STONE WORK
- Unit
- cum
- Source row
- 68
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 1 cum | |||||
| LABOUR | |||||
| 0125 | Mason (for plain stone work) 2nd class) | day | 0.58 | ₹816.00 | ₹473.28 |
| 0115 | Coolie | day | 0.27 | ₹736.00 | ₹198.72 |
Rate build-up
| TOTAL | ₹672.00 |
| Add 1 % Water charges on "W" | ₹6.72 |
| TOTAL | ₹678.72 |
| Add GST on "X" (multiplying factor 0.2127) | ₹144.36 |
| TOTAL | ₹823.08 |
| Add 15% CPOH on "Y" | ₹123.46 |
| TOTAL | ₹946.54 |
| Add Cess @ 1% on "Z" | ₹9.47 |
| Cost of 1 cum. | ₹956.01 |
| Say | ₹956.00 |