DSR 2023 · SH 7 · STONE WORK

CPWD DSR item 7.4.1 rate analysis

Extra for random rubble masonry with hard stone in : Square or rectangular pillars

Published rate₹956.00per cum
Rate analysis

Extra for random rubble masonry with hard stone in :

DSR rate₹956.00per cum

Square or rectangular pillars

Item code
7.4.1
Sub-head
SH 7 · STONE WORK
Unit
cum
Source row
68

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 1 cum
LABOUR
0125 Mason (for plain stone work) 2nd class) day 0.58 ₹816.00 ₹473.28
0115 Coolie day 0.27 ₹736.00 ₹198.72

Rate build-up

TOTAL ₹672.00
Add 1 % Water charges on "W" ₹6.72
TOTAL ₹678.72
Add GST on "X" (multiplying factor 0.2127) ₹144.36
TOTAL ₹823.08
Add 15% CPOH on "Y" ₹123.46
TOTAL ₹946.54
Add Cess @ 1% on "Z" ₹9.47
Cost of 1 cum. ₹956.01
Say ₹956.00