Rate analysis
30 mm red sand stone sun-shade (chisel-dressed) supported on red sand stone brackets, fixed in walls with cement mortar 1:4 (1 cement : 4 coarse sand), including finishing complete.
DSR rate₹2,159.90per sqm
- Item code
- 7.3
- Sub-head
- SH 7 · STONE WORK
- Unit
- sqm
- Source row
- 1383
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Detail of cost for window 1.6m length and | |||||
| 0.70m width = 1.12 sqm. | |||||
| MATERIAL | |||||
| over all width 0.70+0.15=0.85 metres | |||||
| Total area = 1.6x0.85=1.36sqm. | |||||
| Red stone brackets (chisel dressed) 30mm average thickness over all width of brackets | |||||
| 0.53+0.23=0.76m | |||||
| 2x0.3x0.76=0.46 | |||||
| Total 1.36+0.46 =1.82sqm.+ | |||||
| Add wastage @10% = 0.18sqm. | |||||
| Total = 2.00 sqm. | |||||
| 1166 | Red sand stone slab 30 mmthick (un-dressed) | sqm | 2 | ₹300.00 | ₹600.00 |
| 2216 | Carriage of Stone blocks white & red sand stone & kota stone slab | tonne | 0.14 | ₹0.00 | ₹0.00 |
| 9999 | Cement mortar 1 :4 | L.S. | 13.52 | ₹2.27 | ₹30.69 |
| Labour for dressing and fixing: | |||||
| LABOUR | |||||
| 0125 | Mason (for plain stone work) 2nd class) | day | 0.86 | ₹816.00 | ₹701.76 |
| 0114 | Beldar | day | 0.5 | ₹736.00 | ₹368.00 |
Rate build-up
| TOTAL | ₹1,700.45 |
| Add 1 % Water charges on "W" | ₹17.00 |
| TOTAL | ₹1,717.45 |
| Add GST on "X" (multiplying factor 0.2127) | ₹365.30 |
| TOTAL | ₹2,082.75 |
| Add 15% CPOH on "Y" | ₹312.41 |
| TOTAL | ₹2,395.16 |
| Add Cess @ 1% on "Z" | ₹23.95 |
| Cost for 1.12 sqm. | ₹2,419.11 |
| Cost of 1 sqm. | ₹2,159.92 |