DSR 2023 · SH 7 · STONE WORK

CPWD DSR item 7.12.1.1 rate analysis

Stone work in plain ashlar in super structure upto floor five level in cement mortar 1:6 (1 cement : 6 coarse sand) including pointing with cement mortar 1:2 (1 white cement : 2 stone dust) with an admixture of pigment matching the stone shade : One face dressed Red sand stone

Published rate₹68,294.00per cum
Rate analysis

Stone work in plain ashlar in super structure upto floor five level in cement mortar 1:6 (1 cement : 6 coarse sand) including pointing with cement mortar 1:2 (1 white cement : 2 stone dust) with an admixture of pigment matching the stone shade : One face dressed

DSR rate₹68,294.00per cum

Red sand stone

Item code
7.12.1.1
Sub-head
SH 7 · STONE WORK
Unit
cum
Source row
305

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10 cudm.
MATERIAL
Red sand stone
Finished work = 10 cudm.+ Add wastage @ 33.3% = 3.33 cudm. Total = 13.33 cudm
1160 Red sand stone block 10 cudm 1.333 ₹130.00 ₹173.29
2216 Carriage of Stone blocks white & red sand stone & kota stone slab tonne 0.031 ₹0.00 ₹0.00
@ 2.30kg/cudm = 13.33x2.30 = 30.659 kg = 0.03065 tonne. Say 0.031 t.
Extra labour for lifting of materials upto floor V level (0.01x1.50 = 0.015)
0115 Coolie day 0.015 ₹736.00 ₹11.04
Dressing charges
LABOUR
0125 Mason (for plain stone work) 2nd class) day 0.088 ₹816.00 ₹71.81
0102 Blacksmith 1st class day 0.006 ₹897.00 ₹5.38
0114 Beldar day 0.044 ₹736.00 ₹32.38
0115 Coolie day 0.022 ₹736.00 ₹16.19
0100 Bandhani day 0.044 ₹816.00 ₹35.90
Fixing charges
LABOUR
0125 Mason (for plain stone work) 2nd class) day 0.044 ₹816.00 ₹35.90
0102 Blacksmith 1st class day 0.006 ₹897.00 ₹5.38
0114 Beldar day 0.022 ₹736.00 ₹16.19
0115 Coolie day 0.022 ₹736.00 ₹16.19
0100 Bandhani day 0.022 ₹816.00 ₹17.95
0101 Bhisti day 0.022 ₹816.00 ₹17.95
9999 Scafolding L.S. 2.73 ₹2.27 ₹6.20
9999 Mortar for laying and pointing L.S. 8.06 ₹2.27 ₹18.30

Rate build-up

TOTAL ₹480.05
Add 1 % Water charges on "W" ₹4.80
TOTAL ₹484.85
Add GST on "X" (multiplying factor 0.2127) ₹103.13
TOTAL ₹587.98
Add 15% CPOH on "Y" ₹88.20
TOTAL ₹676.18
Add Cess @ 1% on "Z" ₹6.76
Cost of 10 cudm. ₹682.94
Cost of 1 cum. ₹68,294.00
Say ₹68,294.00

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook