DSR 2023 · SH 7 · STONE WORK

CPWD DSR item 7.12.1.2 rate analysis

Stone work in plain ashlar in super structure upto floor five level in cement mortar 1:6 (1 cement : 6 coarse sand) including pointing with cement mortar 1:2 (1 white cement : 2 stone dust) with an admixture of pigment matching the stone shade : One face dressed White sand stone

Published rate₹82,518.00per cum
Rate analysis

Stone work in plain ashlar in super structure upto floor five level in cement mortar 1:6 (1 cement : 6 coarse sand) including pointing with cement mortar 1:2 (1 white cement : 2 stone dust) with an admixture of pigment matching the stone shade : One face dressed

DSR rate₹82,518.00per cum

White sand stone

Item code
7.12.1.2
Sub-head
SH 7 · STONE WORK
Unit
cum
Source row
305

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10 cudm.
MATERIAL
1161 White sand stone block 10 cudm 1.333 ₹205.00 ₹273.27
Finished work = 10 cudm.+ Add wastage @ 33.3% = 3.33 cudm. Total = 13.33 cudm.
2216 Carriage of Stone blocks white & red sand stone & kota stone slab tonne 0.031 ₹0.00 ₹0.00
@ 2.30kg/cudm = 13.33x2.30 = 30.659 kg = 0.03065 tonne say 0.031 t.
Extra labour for lifting of materials upto floor V level. (0.01 x 1.50 =0.015)
0115 Coolie day 0.015 ₹736.00 ₹11.04
Dressing charges
LABOUR
0125 Mason (for plain stone work) 2nd class) day 0.088 ₹816.00 ₹71.81
0102 Blacksmith 1st class day 0.006 ₹897.00 ₹5.38
0114 Beldar day 0.044 ₹736.00 ₹32.38
0115 Coolie day 0.022 ₹736.00 ₹16.19
0100 Bandhani day 0.044 ₹816.00 ₹35.90
Fixing charges
LABOUR
0125 Mason (for plain stone work) 2nd class) day 0.044 ₹816.00 ₹35.90
0102 Blacksmith 1st class day 0.006 ₹897.00 ₹5.38
0114 Beldar day 0.022 ₹736.00 ₹16.19
0115 Coolie day 0.022 ₹736.00 ₹16.19
0100 Bandhani day 0.022 ₹816.00 ₹17.95
0101 Bhisti day 0.022 ₹816.00 ₹17.95
9999 Scaffolding L.S. 2.73 ₹2.27 ₹6.20
9999 Mortar for laying and pointing L.S. 8.06 ₹2.27 ₹18.30

Rate build-up

TOTAL ₹580.03
Add 1 % Water charges on "W" ₹5.80
TOTAL ₹585.83
Add GST on "X" (multiplying factor 0.2127) ₹124.61
TOTAL ₹710.44
Add 15% CPOH on "Y" ₹106.57
TOTAL ₹817.01
Add Cess @ 1% on "Z" ₹8.17
Cost of 10 cudm. ₹825.18
Cost of 1 cum. ₹82,518.00
Say ₹82,518.00