Rate analysis
Extra for coursed rubble masonry with hard stone (first or second sort) curved on plan for a mean radius not exceeding 6 m.
DSR rate₹1,133.65per cum
- Item code
- 7.11
- Sub-head
- SH 7 · STONE WORK
- Unit
- cum
- Source row
- 285
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 1 cum | |||||
| Extra | |||||
| 1157 | Stone for masonry work | cum | 0.11 | ₹1,250.00 | ₹137.50 |
| 2215 | Carriage of Soling stone & masonry stone | cum | 0.11 | ₹0.00 | ₹0.00 |
| Labour for cutting and dressing: | |||||
| 0125 | Mason (for plain stone work) 2nd class) | day | 0.33 | ₹816.00 | ₹269.28 |
| 0115 | Coolie | day | 0.53 | ₹736.00 | ₹390.08 |
Rate build-up
| TOTAL | ₹796.86 |
| Add 1 % Water charges on "W" | ₹7.97 |
| TOTAL | ₹804.83 |
| Add GST on "X" (multiplying factor 0.2127) | ₹171.19 |
| TOTAL | ₹976.02 |
| Add 15% CPOH on "Y" | ₹146.40 |
| TOTAL | ₹1,122.42 |
| Add Cess @ 1% on "Z" | ₹11.22 |
| Cost of 1 cum. | ₹1,133.64 |
| Say | ₹1,133.65 |