DSR 2023 · SH 7 · STONE WORK

CPWD DSR item 7.11 rate analysis

Extra for coursed rubble masonry with hard stone (first or second sort) curved on plan for a mean radius not exceeding 6 m.

Published rate₹1,133.65per cum
Rate analysis

Extra for coursed rubble masonry with hard stone (first or second sort) curved on plan for a mean radius not exceeding 6 m.

DSR rate₹1,133.65per cum
Item code
7.11
Sub-head
SH 7 · STONE WORK
Unit
cum
Source row
285

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 1 cum
Extra
1157 Stone for masonry work cum 0.11 ₹1,250.00 ₹137.50
2215 Carriage of Soling stone & masonry stone cum 0.11 ₹0.00 ₹0.00
Labour for cutting and dressing:
0125 Mason (for plain stone work) 2nd class) day 0.33 ₹816.00 ₹269.28
0115 Coolie day 0.53 ₹736.00 ₹390.08

Rate build-up

TOTAL ₹796.86
Add 1 % Water charges on "W" ₹7.97
TOTAL ₹804.83
Add GST on "X" (multiplying factor 0.2127) ₹171.19
TOTAL ₹976.02
Add 15% CPOH on "Y" ₹146.40
TOTAL ₹1,122.42
Add Cess @ 1% on "Z" ₹11.22
Cost of 1 cum. ₹1,133.64
Say ₹1,133.65