Published rate₹2,874.20per cum
Rate analysis

Circular pillars

DSR rate₹2,874.20per cum
Item code
7.10.2
Sub-head
SH 7 · STONE WORK
Unit
cum
Source row
265

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 1 cum
1157 Stone for masonry work cum 0.32 ₹1,250.00 ₹400.00
2215 Carriage of Soling stone & masonry stone cum 0.32 ₹0.00 ₹0.00
LABOUR
Labour for cutting and dressing :
0125 Mason (for plain stone work) 2nd class) day 1.67 ₹816.00 ₹1,362.72
0115 Coolie day 0.35 ₹736.00 ₹257.60

Rate build-up

TOTAL ₹2,020.32
Add 1 % Water charges on "W" ₹20.20
TOTAL ₹2,040.52
Add GST on "X" (multiplying factor 0.2127) ₹434.02
TOTAL ₹2,474.54
Add 15% CPOH on "Y" ₹371.18
TOTAL ₹2,845.72
Add Cess @ 1% on "Z" ₹28.46
Cost of 1 cum ₹2,874.18
Say ₹2,874.20