DSR 2023 · SH 7 · STONE WORK

CPWD DSR item 7.10.1 rate analysis

Square or rectangular pillars

Published rate₹1,060.50per cum
Rate analysis

Square or rectangular pillars

DSR rate₹1,060.50per cum
Item code
7.10.1
Sub-head
SH 7 · STONE WORK
Unit
cum
Source row
248

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 1 cum
LABOUR
0125 Mason (for plain stone work) 2nd class) day 0.67 ₹816.00 ₹546.72
0115 Coolie day 0.27 ₹736.00 ₹198.72

Rate build-up

TOTAL ₹745.44
Add 1 % Water charges on "W" ₹7.45
TOTAL ₹752.89
Add GST on "X" (multiplying factor 0.2127) ₹160.14
TOTAL ₹913.03
Add 15% CPOH on "Y" ₹136.95
TOTAL ₹1,049.98
Add Cess @ 1% on "Z" ₹10.50
Cost of 1 cum. ₹1,060.48
Say ₹1,060.50