DSR 2023 · SH 7 · STONE WORK

CPWD DSR item 7.8.2 rate analysis

Coursed rubble masonry with hard stone (first or second sort) in superstructure above plinth level and upto floor five level. Masonry work (second sort), in cement mortar 1:6 (1 cement: 6 coarse sand)

Published rate₹10,128.10per cum
Rate analysis

Coursed rubble masonry with hard stone (first or second sort) in superstructure above plinth level and upto floor five level.

DSR rate₹10,128.10per cum

Masonry work (second sort), in cement mortar 1:6 (1 cement: 6 coarse sand)

Item code
7.8.2
Sub-head
SH 7 · STONE WORK
Unit
cum
Source row
185

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 1 cum
MATERIAL
Cement mortar 1 : 6 (1 cement : 6 coarse sand)
3.11 Rate as per Item Number 3.11 of SH: Mortars cum 0.3 ₹3,541.40 ₹1,062.42
1157 Stone for masonry work cum 1.1 ₹1,250.00 ₹1,375.00
1154 Through and bond stone size 24 x24 x39 cm 100 Nos 0.07 ₹5,000.00 ₹350.00
Carriage:
2215 Carriage of Soling stone & masonry stone cum 1.26 ₹0.00 ₹0.00
7.00x24cmx24cmx39cm = 0.16 cum.
1.10+0.16 cum = 1.26 cum.
LABOUR
0125 Mason (for plain stone work) 2nd class) day 2.02 ₹816.00 ₹1,648.32
0114 Beldar day 1.59 ₹736.00 ₹1,170.24
0115 Coolie day 0.71 ₹736.00 ₹522.56
0101 Bhisti day 0.09 ₹816.00 ₹73.44
Extra labour for lifting of material (above floor two level up to floor five level)
0115 Coolie day 1.13 ₹736.00 ₹831.68
9999 Sundries, scaffolding etc. L.S. 37.7 ₹2.27 ₹85.58

Rate build-up

TOTAL ₹7,119.24
Add 1 % Water charges on "W" ₹71.19
TOTAL ₹7,190.43
Add GST on "X" (multiplying factor 0.2127) ₹1,529.40
TOTAL ₹8,719.83
Add 15% CPOH on "Y" ₹1,307.97
TOTAL ₹10,027.80
Add Cess @ 1% on "Z" ₹100.28
Cost of 1 cum. ₹10,128.08
Say ₹10,128.10