Rate analysis
Coursed rubble masonry with hard stone (first or second sort) in superstructure above plinth level and upto floor five level.
DSR rate₹10,128.10per cum
Masonry work (second sort), in cement mortar 1:6 (1 cement: 6 coarse sand)
- Item code
- 7.8.2
- Sub-head
- SH 7 · STONE WORK
- Unit
- cum
- Source row
- 185
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 1 cum | |||||
| MATERIAL | |||||
| Cement mortar 1 : 6 (1 cement : 6 coarse sand) | |||||
| 3.11 | Rate as per Item Number 3.11 of SH: Mortars | cum | 0.3 | ₹3,541.40 | ₹1,062.42 |
| 1157 | Stone for masonry work | cum | 1.1 | ₹1,250.00 | ₹1,375.00 |
| 1154 | Through and bond stone size 24 x24 x39 cm | 100 Nos | 0.07 | ₹5,000.00 | ₹350.00 |
| Carriage: | |||||
| 2215 | Carriage of Soling stone & masonry stone | cum | 1.26 | ₹0.00 | ₹0.00 |
| 7.00x24cmx24cmx39cm = 0.16 cum. | |||||
| 1.10+0.16 cum = 1.26 cum. | |||||
| LABOUR | |||||
| 0125 | Mason (for plain stone work) 2nd class) | day | 2.02 | ₹816.00 | ₹1,648.32 |
| 0114 | Beldar | day | 1.59 | ₹736.00 | ₹1,170.24 |
| 0115 | Coolie | day | 0.71 | ₹736.00 | ₹522.56 |
| 0101 | Bhisti | day | 0.09 | ₹816.00 | ₹73.44 |
| Extra labour for lifting of material (above floor two level up to floor five level) | |||||
| 0115 | Coolie | day | 1.13 | ₹736.00 | ₹831.68 |
| 9999 | Sundries, scaffolding etc. | L.S. | 37.7 | ₹2.27 | ₹85.58 |
Rate build-up
| TOTAL | ₹7,119.24 |
| Add 1 % Water charges on "W" | ₹71.19 |
| TOTAL | ₹7,190.43 |
| Add GST on "X" (multiplying factor 0.2127) | ₹1,529.40 |
| TOTAL | ₹8,719.83 |
| Add 15% CPOH on "Y" | ₹1,307.97 |
| TOTAL | ₹10,027.80 |
| Add Cess @ 1% on "Z" | ₹100.28 |
| Cost of 1 cum. | ₹10,128.08 |
| Say | ₹10,128.10 |