Rate analysis
Brick work 7 cm thick with common burnt clay F.P.S. (non modular) brick of class designation 7.5 in cement mortar 1:3 (1 cement : 3 coarse sand) in superstructure above plinth level and upto floor five level.
DSR rate₹865.65as per item analysis
- Item code
- 6.8
- Sub-head
- SH 6 · MASONRY WORK
- Unit
- See analysis
- Source row
- 290
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 10sqm. | |||||
| MATERIAL | |||||
| 2602 | Common burnt clay F.P.S. (non modular) bricks class designation 7.5 | 1000 Nos | 0.377 | ₹4,724.00 | ₹1,780.95 |
| Cement mortar 1:3 | |||||
| 3.8 | Rate as per Item Number 3.8 of SH: Mortars | cum | 0.181 | ₹4,881.95 | ₹883.63 |
| 2201 | Carriage of Bricks | 1000 Nos | 0.377 | ₹0.00 | ₹0.00 |
| LABOUR | |||||
| 0123 | Mason 1st class | day | 0.72 | ₹897.00 | ₹645.84 |
| 0124 | Mason 2nd class | day | 0.72 | ₹816.00 | ₹587.52 |
| 0115 | Coolie | day | 1.76 | ₹736.00 | ₹1,295.36 |
| 0101 | Bhisti | day | 0.36 | ₹816.00 | ₹293.76 |
| 9999 | Sundries and scaffolding | L.S. | 7.15 | ₹2.27 | ₹16.23 |
| Extra labour for lifting of material (above floor two level up to floor five level) (10x0.07x1.13=0.79) | |||||
| 0115 | Coolie | day | 0.79 | ₹736.00 | ₹581.44 |
Rate build-up
| TOTAL | ₹6,084.73 |
| Add 1 % Water charges on "W" | ₹60.85 |
| TOTAL | ₹6,145.58 |
| Add GST on "X" (multiplying factor 0.2127) | ₹1,307.16 |
| TOTAL | ₹7,452.74 |
| Add 15% CPOH on "Y" | ₹1,117.91 |
| TOTAL | ₹8,570.65 |
| Add Cess @ 1% on "Z" | ₹85.71 |
| Cost for 10 sqm. | ₹8,656.36 |
| Cost for 1 sqm. | ₹865.64 |
| Say | ₹865.65 |