Rate analysis
Providing half brick masonry with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in cement mortar 1:3 (1 Cement : 3 coarse sand) in superstructure for closing cavity 5 to 7.5 cm wide in cavity wall complete with 10cm / 11.4 cm wide bitumen felt type 3 grade 1.
DSR rate₹300.75as per item analysis
- Item code
- 6.7
- Sub-head
- SH 6 · MASONRY WORK
- Unit
- See analysis
- Source row
- 262
Cost components
| Code | Description | Unit | Quantity | Rate | Amount |
|---|---|---|---|---|---|
| Details of cost for 10m length | |||||
| MATERIAL | |||||
| Half brick masonry 1:3 (Average) | |||||
| 1x10x0.27 = 2.7 | |||||
| 6.12.1 | Rate as per item No. 6.12.1 of SH: Brick Work | sqm | 2.7 | ₹931.75 | ₹2,515.73 |
| Bitumen felt type- 3 grade 1 | |||||
| 1x10mx11.4m = 1.14 sqm. | |||||
| Add for wastage and overlapping @ 5% = 0.06 sqm. | |||||
| Total = 1.20 sqm | |||||
| 0322 | Bitumen felt :Type 3 grade 1 | sqm | 1.2 | ₹80.00 | ₹96.00 |
| LABOUR | |||||
| 0123 | Mason 1st class | day | 0.12 | ₹897.00 | ₹107.64 |
| 0124 | Mason 2nd class | day | 0.12 | ₹816.00 | ₹97.92 |
| 0114 | Beldar | day | 0.06 | ₹736.00 | ₹44.16 |
Rate build-up
| TOTAL | ₹2,861.45 |
| Add 1 % Water charges on "W-A" | ₹3.46 |
| TOTAL | ₹2,864.91 |
| Add GST on "X-A" (multiplying factor 0.2127) | ₹74.27 |
| TOTAL | ₹2,939.18 |
| Add 15% CPOH on "Y-A" | ₹63.52 |
| TOTAL | ₹3,002.70 |
| Add Cess @ 1% on "Z-A" | ₹4.87 |
| Cost of 10 metre | ₹3,007.57 |
| Cost for 1 metre | ₹300.76 |
| Say | ₹300.75 |