DSR 2023 · SH 6 · MASONRY WORK

CPWD DSR item 6.9 rate analysis

Brick work in plain arches in superstructure above plinth level and upto floor five level including centering and shuttering complete for span up to 6 metres with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in cement mortar 1:3 (1 cement : 3 coarse sand).

Published rate₹15,077.95DSR 2023
Rate analysis

Brick work in plain arches in superstructure above plinth level and upto floor five level including centering and shuttering complete for span up to 6 metres with common burnt clay F.P.S. (non modular) bricks of class designation 7.5 in cement mortar 1:3 (1 cement : 3 coarse sand).

DSR rate₹15,077.95as per item analysis
Item code
6.9
Sub-head
SH 6 · MASONRY WORK
Unit
See analysis
Source row
318

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 1 cum.
MATERIAL
2602 Common burnt clay F.P.S. (non modular) bricks class designation 7.5 1000 Nos 0.494 ₹4,724.00 ₹2,333.66
Cement mortar 1:3
3.8 Rate as per Item Number 3.8 of SH: Mortars cum 0.25 ₹4,881.95 ₹1,220.49
2201 Carriage of Bricks 1000 Nos 0.494 ₹0.00 ₹0.00
9999 Sundries L.S. 2.73 ₹2.27 ₹6.20
Centring and shuttering
Taking a semi circular arch 3.6m span,
3.6m long and 0.40m thick
Area of centering = 3.142 x 1.8 x 3.6 = 20.37 sqm.
Brick work in Arch = 3.142x2.00x0.4x3.6 = 9.05cum.
Area per cum = 20.37/9.05 = 2.25 sqm
5.9.9 Rate as per item no 5.9.9 of SH : Reinforced cement concrete work sqm 2.25 ₹2,154.35 ₹4,847.29
9999 Scaffolding L.S. 18.85 ₹2.27 ₹42.79
LABOUR
0123 Mason 1st class day 0.53 ₹897.00 ₹475.41
0124 Mason 2nd class day 0.53 ₹816.00 ₹432.48
0115 Coolie day 2.29 ₹736.00 ₹1,685.44
0101 Bhisti day 0.2 ₹816.00 ₹163.20
Extra labour for lifting of material (above floor two level up to floor five level)
0115 Coolie day 1.13 ₹736.00 ₹831.68

Rate build-up

TOTAL ₹12,038.64
Add 1 % Water charges on "W-A" ₹71.91
TOTAL ₹12,110.55
Add GST on "X-A" (multiplying factor 0.2127) ₹1,544.90
TOTAL ₹13,655.45
Add 15% CPOH on "Y-A" ₹1,321.22
TOTAL ₹14,976.67
Add Cess @ 1% on "Z-A" ₹101.29
Cost for 1 cum. ₹15,077.96
Say ₹15,077.95

Use this rate in the interactive workbook

Search, temporarily edit basic rates, recalculate dependencies, and export from the existing DSR workbook.

Open DSR Workbook