DSR 2023 · SH 6 · MASONRY WORK

CPWD DSR item 6.41 rate analysis

Extra for Gypsum panel Partitions in superstructure above floor V level for every four floors or part thereof.

Published rate₹181.15DSR 2023
Rate analysis

Extra for Gypsum panel Partitions in superstructure above floor V level for every four floors or part thereof.

DSR rate₹181.15as per item analysis
Item code
6.41
Sub-head
SH 6 · MASONRY WORK
Unit
See analysis
Source row
1448

Cost components

CodeDescriptionUnitQuantityRateAmount
Details of cost for 10 sqm. per four floor
Extra labour element for lifting of materials above floor V level.
0115 Coolie day 1.73 ₹736.00 ₹1,273.28

Rate build-up

TOTAL ₹1,273.28
Add 1 % Water charges on "W" ₹12.73
TOTAL ₹1,286.01
Add GST on "X" (multiplying factor 0.2127) ₹273.53
TOTAL ₹1,559.54
Add 15% CPOH on "Y" ₹233.93
TOTAL ₹1,793.47
Add Cess @ 1% on "Z" ₹17.93
Cost for 10 sqm. ₹1,811.40
Cost for 1 sqm ₹181.14
Say ₹181.15